Corporate Social Responsibility | Business Wire | PR NewsWire | Marketwire | Realwire | ACN/JCN newswire | 247pressrelease | PRWeb

Baja Mining Provides Project Update

Posted : Wed, 28 Oct 2009 18:12:08 GMT
Author : Baja Mining Corp.
Category : Press Release
News Alerts by Email ( click here )
News | Home
VANCOUVER, BRITISH COLUMBIA -- 10/28/09 -- Baja Mining Corp. (TSX: BAJ)(OTCQX: BAJFF) is pleased to provide shareholders with an update on the Company and its Boleo Project in Baja California Sur, Mexico.

Boleo contains a large copper deposit with significant quantities of cobalt, zinc and manganese. The mine plan envisages a long-life, low-cost operation in a mining-friendly jurisdiction.

Capital Cost and Construction Financing

In April 2009, the Company appointed ICA Fluor, a joint venture between U.S.-based Fluor Corporation and Empresas ICA of Mexico, to perform the engineering, procurement and construction management (EPCM) for Boleo. ICA Fluor began work on Phase I of the EPCM contract in May 2009 by developing an open book capital cost estimate and project construction schedule. The capital cost estimate was expected to be completed by the end of the third quarter of 2009.

"Although slightly delayed, the further investment of time in this review is both necessary and value-adding. I want to assure shareholders that Baja and ICA Fluor have been working hard, including conducting further detailed engineering, to complete the review as soon as possible. It is being done with a thoroughness that will ensure its accuracy and value," says John Greenslade, President and CEO of Baja.

"The capital cost estimate, expected to be released shortly after a final review by the Company, will form the basis for how project financing is structured and negotiated," he says.

ICA Fluor will continue to advance detailed engineering to ensure the accuracy of costs associated with the estimate and to facilitate construction of the mine site and process plant next year.

Also, Baja has been working with its financial advisor, Endeavour Financial International Corporation, to implement an optimum financing package for construction of Boleo. The Company has had significant interest from senior lenders and development agencies.

"A number of key interested parties have visited the Boleo mine site and are continuing their due diligence. They will require time to review the updated capital cost estimate once it is finalized," says Mr. Greenslade.

Mr. Greenslade also commented that "We are working diligently on this process and anticipate we will be able to announce details of our progress in the near future."

Mobilization of Equipment

The steam turbine for an electricity co-generation facility to be installed at Boleo has been mobilized from Siemens' manufacturing plant in the Czech Republic to its European point of departure in Antwerp, Belgium. The steam turbine will depart for its holding destination, Houston, Texas, in November 2009. It will be moved to site once construction on the process plant begins. The co-generation facility harnesses the energy, generated within the sulphuric acid manufacturing process, to drive a steam turbine that will provide the majority of the power required for operations at Boleo. Pictures of the Boleo steam turbine can be found at http://www.bajamining.com/boleo/pictures/.

The Company expects further preliminary mobilization of equipment to commence later in the year. Construction is expected to re-commence in the first half of 2010, upon completion of construction financing.

Other Activities at Boleo

To date in 2009, Baja also:

- Completed 75% of the Phase 1 1,000-worker construction camp on site.

- Installed a desalinization plant to service the construction camp.

- Moved initial complements of materials and equipment to site.

- Maintained site security and services with all equipment and buildings in working order.

- Conducted geotechnical drilling for placement of a tailings dam.

- Investigated sourcing of raw material supplies including sulphur.

- Continued work on reducing the technical risk at Boleo.

- Upheld its commitments on long lead-time equipment.

- Continued its recruitment of key individuals at site.

- Opened an office in the nearby town of Santa Rosalia to facilitate good community relations and efficient project development.

- Advanced work to enable a decision to initiate manganese production once mining has commenced and the plant is up and running.

- Advanced corporate infrastructure, controls and management information systems.

Community Relief Efforts

In August this year, the Baja Peninsula was struck by Hurricane Jimena. The town of Santa Rosalia required assistance in recovering from damage caused by flooding. The Company has aided in the clean up of the town, provided potable water, food and medical supplies. There was no significant damage to the Boleo Project site.

Management Recognition

Dr. David Dreisinger, Baja's Vice President - Metallurgy, has been elected as a Fellow of the Canadian Institute of Mining, Metallurgy and Petroleum (CIM). Dr. Dreisinger is an internationally renowned expert in hydrometallurgy, a long-time professor at the University of British Columbia and holds the Industrial Research Chair in Hydrometallurgy at the university. He has been involved with Baja since the 1990s and has been instrumental in developing the process flow sheet for Boleo. He is now supporting the efforts of Baja's resident manganese expert, Dr. Thomas Gluck, in developing manganese production at Boleo.

Baja Mining is a Vancouver-based publicly traded mine development company (TSX: BAJ)(OTCQX: BAJFF) with a 70% interest in the Boleo copper-cobalt-zinc-manganese project located near Santa Rosalia, Baja California Sur, Mexico. A Korean syndicate holds the remaining 30%. Baja is the project operator. The target date for commissioning Boleo is 2012. A 2007 definitive feasibility study projected an average annual production for the first four years of 56,000 tonnes of copper cathode, 1,500 tonnes of cobalt cathode and 20,000 tonnes of zinc sulphate. The project has proven and probable reserves that support a mine life of more than 25 years. Anticipated cash costs in the first five years are US$0.27 per pound of copper, net of by-product credits for cobalt and zinc, and with no credit for manganese.

ON BEHALF OF THE BOARD OF DIRECTORS OF BAJA MINING CORP.

JOHN W. GREENSLADE, PRESIDENT

Some of the statements contained in this release are forward-looking statements, such as statements that describe the Company's, expected timing of project commissioning, expected greater access to capital investment markets, anticipated cash costs in the first five years and other statements. Since forward-looking statements are not statements of historical fact and address future events, conditions and expectations, forward-looking statements by their nature inherently involve unknown risks, uncertainties, assumptions and other factors well beyond the Company's ability to control or predict. Actual results and developments may differ materially from those contemplated by such forward-looking statements. Material factors that could cause actual revenues to differ materially from those contained in such forwarding-looking statements include (i) fluctuations on the prices of copper, cobalt, zinc and manganese, (ii) interpretation of contract terms, (iii) accuracy of the Company's and consultants' projections, (iv) the Company's ability to finance, receive permits for, obtain equipment, construct and develop the El Boleo Project, (v) the effects of weather; operating hazards; adverse geological conditions and global warming, (vi) impact of availability of labor, materials and equipment; and (vii) changes in governmental laws, regulations, economic conditions or shifts in political attitudes or stability.

These forward-looking statements represent the Company's views as of the date of this release. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Readers should not place undue reliance on any forward-looking statements.

Contacts:
Baja Mining Corp.
John Greenslade
President
604-685-2323
604-629-5228 (FAX)
www.bajamining.com


Copyright © 2008 Market Wire. All rights reserved.
Share/Save/Bookmark



Related News

World Food Invests in Energy
World Food Association Organization is looking towards green alternative energy projects to pioneer the change in our planet's climate. The massive project is no small undertaking and World Food Association Organization has taken the helm position to ensure that it comes to fruition./I/P ...

First Gold Hires Investor Relations Firm
LAVAL, QUEBEC -- 11/26/09 -- First Gold Exploration Inc. (TSX VENTURE: EFG)(FRANKFURT: F12) is pleased to announce that it has engaged the services of National Media Associates, an independent firm of investor relations. National Media Associates w..

Media Release-KAIROS Partners Murdered in Philippines: A Response to the Massacre
TORONTO, ONTARIO -- 11/26/09 -- Attention: Religion, Foreign, and Human Rights Journalists KAIROS: Canadian Ecumenical Justice Initiatives condemns the murder of 57 people in the Philippines, including two of its human rights partners, an..

Brompton Funds Announces Investor Conference Calls with Portfolio Manager: MFC Global Investment Management
TORONTO, ONTARIO -- 11/26/09 -- Brompton Funds (TSX: AOG.UN)(TSX: AOG.WT.A) (TSX: AV.UN)(TSX: AV.WT.A) (TSX: MBB.UN)(TSX: OGF.UN)(TSX: OGF.WT.A)(TSX: VIP.UN)(TSX: VIP.WT.A) is pleased to announce that it will be hosting three investor conference ca..

Ventana Provides Corporate Development Update and Announces Dispute Respecting La Bodega Agreement
VANCOUVER, BRITISH COLUMBIA -- 11/26/09 -- Ventana Gold Corp. (TSX: VEN) ("Ventana" or "the Company") has been advised that Sociedad Minera La Bodega Limitada (or the "Vendor"), the owner of the mineral rights to the La Bodega property in Colombia,..

BioSyent Releases 2009 Third Quarter Financial Results
MISSISSAUGA, ONTARIO -- 11/26/09 -- BioSyent Inc. ("BioSyent")(TSX VENTURE: RX) today released a summary of its 2009 third quarter financial results. During the third quarter ended September 30, 2009 sales increased by 17%, from $431,841 ..

Pacific Safety Products Inc. Announces Fiscal Year 2010 First Quarter Results
KANATA, ONTARIO -- 11/26/09 -- Pacific Safety Products Inc. (TSX VENTURE: PSP) ("PSP" or "the Company") today announced consolidated financial results for the three month period ended September 30, 2009. Recent Developments: - R..

Have your Say
Name
Email
Subject
Your Comment

Enter Verification code
 
  

 
Follow The Earth Times
Subscribe to RSS Follow Earth Times on TwitterNews by email
Share/Save/Bookmark
 
 



 
Subscribe to free Earthtimes
News Alerts by Email Click here
For RSS Feeds Click here
or Create your own RSS

Add to Google Toolbar
Breaking News
Press Releases

 


The Earth Times
News Category

© 2009 www.earthtimes.org, The Earth Times, All Rights Reserved | Privacy Policy
Earth Times accept no responsibility or liability either directly or indirectly for views or opinions expressed in articles or comments.